Primetals Technologies
Shougang Qian’an’s and Primetals Technologies’ project team.

2026年11月18日

Primetals Technologies Receives Final Acceptance for Automation Upgrade at Shougang Hot Strip Mill No. 1

新闻

热带钢轧机

热轧

  • Full production achieved just ten days after the annual maintenance shutdown
  • Quality targets exceeded across a wider range of products
  • Early detection of process deviations with the Diagnostic Plug, supporting ongoing operational optimization

Primetals Technologies has recently received the final acceptance certificate (FAC) for the Level 2 automation upgrade of Hot Strip Mill No. 1 at Shougang Qian'an Iron & Steel Co. in China. The project included modernizing the existing Level 2 system and selected Level 1 functions for the reversing roughing stands, the six-stand finishing mill, the sizing press and the coil box.

Improved Product Quality and Process Performance

The upgrade extends the material database, so a broader range of steel grades can now be modeled with higher accuracy. Modern process models enable more precise calculations and predictions and helped the mill clearly exceed the agreed performance targets. Several customer-specific functions were implemented, and the mill's cooling strategies were further refined.

Process engineers gain earlier insight into process and quality data through the Diagnostic Plug, an advanced analysis and diagnostic tool. It makes deviations visible early, so maintenance engineers can respond quickly and optimize operations on an ongoing basis.

With the implementation of the Contour and Flatness Optimizer, Shougang's hot strip mill has reached a new level of strip shape control. Advanced process models, adaptive learning, and coordinated actuator control deliver superior profile and flatness performance, resulting in improved product consistency and operational stability.

Fast and Low-Risk Production Ramp-Up

Primetals Technologies teams combined their modeling and commissioning expertise with Shougang’s engineers to deliver an integrated approach from modeling through commissioning. A key highlight was the preparation for production ramp-up. The model was intensively trained during a four-week shadow-mode operation to ensure a smooth start. Level 2 commissioning was then completed within a scheduled ten-day annual maintenance shutdown.

Within the first five production days, the mill reached about 90 percent of its average daily output. Just ten days after the first coil, it was running at full production capacity.

Letter of Thanks and Future Steps

Shougang has thanked Primetals Technologies with a formal Letter of Thanks for the professional execution of the project and the excellent cooperation. The next step is already in sight: further collaboration under an Electrics and Automation service agreement is planned.

Shougang Qian'an's offers a full range of cold- and hot-rolled steel products, including electrical steel, automotive steel, pipeline steel, and sheet for the home appliance industry, along with value-added services.

Shougang Qian’an’s and Primetals Technologies’ project team.

Shougang Qian’an’s and Primetals Technologies’ project team.

First coil rolled at Shougang’s site.

First coil rolled at Shougang’s site.

普锐特冶金技术有限公司(Primetals Technologies, Limited)总部位于英国伦敦,是一家专注于冶金行业工程设计、工厂建设及全生命周期服务的国际化企业。 我们提供全面的技术、产品及服务,包括整合电气、自动化,数字化和环境解决方案。 涵盖了钢铁产业链从原材料到成品的每一项环节,以及适用于有色金属领域的最新轧制解决方案。 普锐特冶金技术是三菱重工旗下集团公司,全球约有7,000名员工。 如需进一步了解普锐特冶金技术,请访问公司网站www.primetals.com。

*本页面提供的资料可供媒体及合作伙伴在报道普锐特冶金技术时使用。 请注明出处。

注册即可获取实时新闻更新

实时了解普锐特冶金技术的最新资讯与新闻 —— 涵盖创新成果、项目进展及行业见解。

Contact Person

新闻

热带钢轧机

热轧

自动化

数字化

佩戴耳机的客服代表

请随时联系我们!

如需了解更多解决方案和相关服务, 联系我们——我们随时为您服务!

第一时间掌握普锐特冶金技术最新动态!

订阅普锐特冶金技术新闻通讯,及时获取我们的专业洞察、行业趋势和最新资讯,助您始终领先一步。 立即订阅!